Project updates

November 29, 2021

All pipe work in Cove Road, Fleet, is now complete and our workforce will be moving onto Fleet Road.

We're continuing to make good progress installing new pipe along Bagwell Lane, Odiham, and more than 1.8 kilometres of water main has been installed in the area so far.

November 19, 2021

Our major, multi-million pound pipeline project has hit its first milestone two weeks ahead of schedule.

We’re delighted to report all the first phase of new pipe has now been installed within Cove Road.

This means we can lift the road closure ahead of time and move onto the next phase of the scheme in Fleet Road from Monday, 29 November.

Our road closure in Cove Road will be lifted later this evening (Friday 19 November), meaning residents and commuters will be able to use the road as normal.

We’re really sorry for any disruption this vital work may have caused and would like to thank everyone for their continued patience.

November 12, 2021

Following a successful drop-in session with residents in Elvetham Heath and discussions with Hartley Wintney Parish Council, we have made some amendments to our program.

Work is still planned to begin in Fleet Road later this month however we will be starting at its junction with Pale Lane, working towards Reading Road.

This first section will be carried out using temporary traffic lights in order to minimise disruption to the local community.

Work will continue until 12 December, at which point all works in Fleet Road will stop as agreed by Hampshire Highways. This is to ensure we avoid causing disruption during the busy festive period.

Our workforce will return to Fleet Road on 10 January 2022, at which point a road closure will be in place.

We’re very sorry for any disruption this may cause and we are really grateful for your continued patience while we carry out this vital work.

November 8, 2021

We've continued to make good progress installing new water main in Bagwell Lane, Odiham and Cove Road, Fleet.

More than 2.5 kilometres of pipe has been installed across the project so far.

October 20, 2021

We're inviting Elvetham Heath residents to join us at a public information session in November.

Our project team will be at the Key Centre, The Ky, Fleet, from 7pm until 9pm on 10 November.

We will gladly answer any questions you have about the project.

For more information, click here.

October 15, 2021

We have continued to make good progress with installing the new water pipe and more than 2 kilometres of new main has been laid so far.

We recently carried out an exciting environmental project as part of this vital work - using detection dogs to help us locate great crested newts and protect them from our construction area.

You can find out more here.

September 17, 2021

We've continued to make good progress this week and our workforce has installed 1.6 kilometres of water main in total so far.

The maps below show where the road closures are currently situated and we're grateful for the patience shown by residents during this vital work.

September 10, 2021

Our £10 million project to install 12 kilometres of pipe between Fleet and Odiham, Hampshire, continues to make good progress with more than 1.5 kilometres of pipe laid so far.

From next week, Cove Road West will be closed to motorists as we continue to lay pipe in the area.

We’re really sorry for any disruption caused and would like to thank residents for their continued patience during this vital project.

September 3, 2021

We’re making good progress with our project to install new water main along Cove Road – forming part of a wider scheme to lay 12 kilometres of pipe between Fleet and Odiham.

Our workforce is working slightly ahead of our planned schedule and therefore we plan to close Cove Road west of Ancells Roundabout earlier than planned.

Cove Road is now planned to be shut west of the roundabout from Monday 13 September. Once the western section is closed, the eastern side will be opened. However, motorists should still use our signed diversion route as Ancells Road is not suitable for diverted traffic.

We will no longer need to use temporary traffic lights in Cove Road East as we originally anticipated.

We’re really grateful for the patience shown by customers and motorists so far and we are very sorry for any disruption the road closure may be causing.

 

August 27, 2021

Our workforce is now approaching the roundabout linking Cove Road and Ancells Road.

We anticipate construction within the roundabout section will begin on Monday 6 September and will last for approximately two weeks.

Due to existing utilities in the road, we cannot cross the roundabout along the main road. Therefore, our plan is to use the slip road to Old Cove Road to continue installing the new pipe.

Unfortunately, this does mean parking directly outside of properties may be restricted, but access to driveways will always be maintained.

We are really sorry for the disruption this section of work may cause and we are very grateful for the patience shown by residents so far.

August 23, 2021

We have now installed more than one kilometre of water main across the scheme as we continue to make good progress.

The maps below indicate where the road closures in both Bagwell Lane and Cove Road are currently situated. Once again, we're really sorry for any disruption these may cause.

August 6, 2021

Our workforce made great progress throughout July and will continue to lay pipe in Cove Road and Bagwell Lane throughout August.

The maps below show where our road closures are currently situated and we are really sorry for any disruption caused.

July 30, 2021

We have made good progress throughout July and our workforce has installed more than 600 metres of water main in total since the project started.

The maps below show where our road closures are currently based and we apologise for any disruption these may cause.

July 23, 2021

Water main installation continued this week and we have installed more than 400 metres of pipe in total so far.

We're really grateful for the patience shown by the community and the kindness towards our workforce while we carry out this vital work.

July 16, 2021

We’ve continued to make good progress with this vital project to protect drinking water supplies in Hampshire.

Our workforce has installed 213 metres of pipe in Poland Lane and Bagwell Lane combined while 60 metres of main has been installed so far along Cove Road.

Thank you to our customers for their continued patience as the works progress.

July 09, 2021

Our workforce has continued to make good progress with pipe installation this week. Work in Poland Lane is now complete and we have commenced pipe laying in Cove Road and Bagwell Lane.

So far, 20 metres of new water main has been installed in Cove Road and 165 metres combined in Poland Lane and Bagwell Lane.

The maps below indicate where the road closures are currently situated in both Cove Road and Bagwell Lane. We're very sorry for the disruption caused and would like to thank our customers for their continued patience.

July 02, 2021

We’re making good progress and work in Cove Road, Fleet, is due to commence on Monday, July 5. Cove Road will be closed east of Ancells Road roundabout for a period of approximately 21 weeks and a clearly signed diversion route is in place.

Work will also begin in Bagwell Lane, Hook, from next week and the road will be closed for approximately 33 weeks. We’re really sorry for any disruption these road closures may cause.

Meanwhile, our work in Poland Lane, Hook, completed on Wednesday (30 June) and our workforce is currently working at the junction of Odiham Road and Bagwell Lane under temporary, four-way traffic lights.

June 25, 2021

We’ve been making good progress with our pipe installation work in Poland Lane and we have installed 70 metres of water main so far.

We were due to complete work in Poland Lane yesterday (Friday) but an unforeseen delay means we are working slightly behind our planned schedule.

Work will continue in Poland Lane until Wednesday, June 30 under the same traffic management conditions.

Once complete, four-way traffic lights will be installed at the junction of Poland Lane and Odiham Road to enable our workforce to continue laying pipe towards Bagwell Lane.

We are really sorry for the disruption this delay may cause and we are very grateful for the patience shown by residents so far.

June 2, 2021

Our interactive map is a great tool to receive text and/or email alerts about this project. Click here to sign up.

We're currently installing more than 11 kilometres of water main between Fleet and Odiham, Hampshire.

This investment, more than £10 million in total, was identified as a high priority due to the predicted increase in population and demand in the coming years.

To reinforce our network and draw in larger volumes of water from other areas of our underground system, we need to install the new pipe before April 2023.

The route identified takes the pipe through Cove Road, Fleet Road, Bagwell Lane and Elvetham Heath Way in Fleet. Pipe is also to be laid in Pale Lane, Bagwell Lane, Dunleys Hill and Odiham Road, Hook. Other impacted roads include Poland Lane, Winchfield and The Hurst.

Route map

A mixture of traffic management measures will be in place to keep the public and our workforce safe throughout the project, including a series of road closures.

There will also be a short section of work within North Hants Golf Club in late 2022 into early 2023 which will require Cove Road to be closed for a second time to allow space for large machinery to be safely positioned.

Work started in June 2021 and we anticipate the project will be complete by April 2023, although our workforce will work as quickly and safely as possible to reduce the length of the scheme.

A virtual customer engagement event was held in April and anyone who was unable to attend can download a copy of the presentation here. A list of frequently asked questions and answers can be found at the bottom of this web page.

You can also watch a recording of the presentation by clicking here.

Project timetable

Location

Start Date

Approx Duration

Planned end date

Traffic management plans

Bagwell Lane 

1/7/21

37 weeks and four days

22/3/22

Road closure

Fleet Road (Pale Lane Junction)

29/11/21

2 weeks

12/12/21

Temporary traffic lights

Bogs Road crossing

TBC

2 days

TBC

Stop and go

Fleet Road

10/01/22

10 weeks and 4 days

25/03/22

Road closure and traffic lights

Total Fleet Road section

29/11/21

16 weeks and 4 days (No works between 12 December and 10 January to minimise disruption over the festive period)

25/03/22

Road closure and traffic lights

Taplins Farm Road crossing

10/1/22

3 days

13/1/22

4-way lights

The Hurst

14/1/22

7.5 weeks

28/3/22

Road closure

Elvetham Heath Way

29/3/22

4 days

1/4/22

4-way lights

Elvetham heath way roundabout

4/4/22

6 days

8/4/22

4-way lights

Elvetham way footpath

01/06/2022

43 weeks

25/03/23

Footpath closure

Total Elvetham Heath Way section

29/3/22

52 weeks

25/03/23

4-way lights and footpath closure

Winchfield Road (Station Road)

23/3/22

11 weeks

15/7/22

Road closure

Dunleys Hill

20/6/22

4 days

24/6/22

Road closure and traffic lights

Pale Lane

18/7/22

10 weeks

31/10/22

Road closure

Cove Road phase 2 (closed to allow drilling rig for golf course)

11/10/22

12 weeks

10/01/2023

Road closure

Diversion routes

Fleet Road

The Hurst

Dunleys Hill

Bagwell Lane

Pale Lane

Winchfield Road (Station Road as known locally)

Frequently asked questions

What are we doing?

We’re installing 12 kilometres of water main between Fleet and Odiham. We anticipate the project will take approximately 21 months to complete.

 

Where is it?


Construction work will take place along Cove Road, Fleet Road and Elvetham Heath Way in Fleet. Pipe will also be laid in Pale Lane, Dunleys Hill, Poland Lane, Bagwell Lane and Odiham Road, Hook. Other impacted roads include Winchfield Road and The Hurst.


Will we be closing the road?

For safety reasons this project will involve a series of road closures. While we know road closures can be frustrating it is vital we prioritise the safety of both the public and our workforce. Details on road closures and diversion routes can be found on our website. All road closures and diversion routes have been agreed by Hampshire County Council’s Highways team.

 

How will I get to my house?

Access to homes and businesses will always be available, however your access point may change depending on where the working area is. Our team will deliver cards through your door to let you know when the working area is moving and you can speak to the crew on site if you have any concerns.

 

How will the closure impact the buses?

We’ve been in close communication with bus companies throughout the planning phase of the project and any changes to bus stop locations or timetables will be available on the website.

 

What is the aim of the project?

We need to strengthen the water network in the area to help us to continue to supply top-quality drinking water as the community grows.

 

Will the water supply be interrupted?

We do not anticipate any interruption to supply as a result of this work. If for any reason we do need to switch off customer water supplies we will notify you well in advance.

 

I have additional needs and I require extra support

Customers with additional needs be it a disability, mental health or financial concerns can sign up to our Priority Services Register to help us understand how we can help you. More information can be found at: southeastwater.co.uk/priority


How can I find out more information?

We provide regular updates on the project on our dedicated webpage: corporate.southeastwater.co.uk/fleet, you can also sign up for updates using our In Your Area map. We also provide updates on our Facebook and Twitter pages. You may also read about the project through the local media.

How have you communicated the scheme?

We sent letters to local residents and businesses and held a virtual customer information event on April 19th, 2021. This gave our customers a chance to see the project plans in detail and ask questions to the project team. We’ve also been in close contact with our stakeholders and local businesses throughout the planning phase of the project. We provide regular updates on our webpage and on our social media channels.

 

 

Launch Recite Me web accessibility software
^

Return to top