We're installing approximately 200 metres of new water main in Turk Street and Lower Turk Street, Alton, Hampshire.

This scheme is necessary to improve the capacity of the network and ensure we can continue to maintain water pressure in the area as the community grows.

We are using traditional trenching techniques to install the new section of water main. Construction works are being carried out in stages, with the road being returned to its original state upon completion of one section before the working area moves along to the next stage.

As a safety precaution for pedestrians, motorists and our workforce, temporary traffic lights are in use to enable motorists to use the road while work takes place.

Construction started on 21 March 2022 and the project is expected to take approximately six weeks to complete, however, our workforce will work as hard as they can to complete the work as quickly and safely as possible.