We replaced approximately 274 metres of burst-prone water main in Cavell Avenue North and Firle Road, Peacehaven, in a £155,000 project. This work formed part of our commitment to invest £567 million upgrading our infrastructure between 2020 and 2025.

Work started on Monday 27 November, and took approximately eight weeks to complete.

Project updates



Monday, 25 March 2024
16:14 PM

Project completed

We’ve now completed this project and the new main is now commissioned and in service. Thank you to the local community for your patience while we undertook this vital work.


Tuesday, 27 February 2024
11:17 AM

All new water main has now been installed and the pipeline has been brought into service. We have left the site but will be back to complete the last remaining tasks to ensure the working area is returned to its original state.


Monday, 8 January 2024
09:15 AM

Works have resumed after the Christmas break and we have continued to excavate for the next 50m of pipework. We have also prepared to transfer 10 services to the new main.

A leak was found and repaired while we made a connection to the existing network.


Monday, 4 December 2023
14:44 PM

We started work as planned last Monday and have started excavations in preparation for directional drilling later this week.