As part of our ongoing programme to improve our water supply network, we're installing 900 metres of new water pipe in Brookhouse Bottom and Perryman’s Lane, Uckfield.
This vital, £400,000 investment will replace an ageing and unreliable water pipe which has been prone to water quality issues in recent years and has also suffered three bursts, causing significant disruption to local residents.
Work started on 6 June and is expected to take five months to complete.
As a safety precaution for pedestrians, motorists and our workforce, we have closed Brookhouse Bottom and Perryman’s Lane to through traffic only. Diversion routes are clearly signed.
Access to homes and businesses will be maintained throughout the project.
Project Updates
Monday, 17 October 2022
07:47 AM
Project complete
We’re pleased to say that this scheme has now finished, with all services now transferred to the new main and the site returned to its original state.
Monday, 10 October 2022
16:27 PM
The final two services have been excavated ready to connect to the new main. Pressure testing and water quality samples all passed and so connections will be completed this week and we will start clearing our site.
Tuesday, 4 October 2022
13:56 PM
We’ve laid the final 16m of pipe, which means the full length of new main has now been laid. This week, we’ll be testing the main ahead of transferring all services.
Tuesday, 27 September 2022
14:43 PM
A further 62m of new main was laid this week. The last section of pipework will be laid this week ready for testing with service transfers being undertaken once testing is complete.
Wednesday, 14 September 2022
13:52 PM
We’re continuing to reinstate the road where we have already laid pipework. We completed another connection last week and have approximately 90m of main left to lay and final services to transfer.
Monday, 29 August 2022
12:57 PM
We’ve now laid 793 metres to date, with progress being made difficult by dry ground conditions. We appreciate the patience from residents as we continue this vital work.
Tuesday, 9 August 2022
13:48 PM
We’ve now laid 715 metres, and were pleased to be able to work with the local campsite to allow access to around 50 vehicles for parents needing to collect their children – we hope they had a great camping experience.
Monday, 1 August 2022
15:22 PM
We’ve excavated trial holes this week to see if we can continue with directional drilling but the remaining 266m will need to be laid with the traditional open trench method as planned. All mains laid to date have been commissioned and services connected.
Tuesday, 26 July 2022
13:46 PM
Restricted access on Perryman's Lane
We’ve now started works on Perrymans Lane to lay the new section of pipework along this road with restricted access during the working day to ensure that we can complete our works safely.
Monday, 18 July 2022
09:22 AM
Hot weather
There may be times over the coming days when you may see our teams working a little differently. With record breaking hot temperatures forecast, we are advising our teams to be mindful of the conditions, seek shade as and when necessary, or close the site early if conditions become too severe to undertake physical work. We appreciate your patience and assure you the teams will be back on site as normal as soon as possible.
Wednesday, 13 July 2022
14:59 PM
Work area moves along Perryman's Lane
We've now laid approximately 670m of pipework, and are continuing service transfers to the new main.
From Monday, 18 July, we'll be moving the work area along Perryman’s Lane, which will mean that there will be restricted access between 9.00am and 3.00pm, Monday to Friday. This is to ensure the safety of our team whilst working to lay the pipe up to the top of the hill. Our team will be in the middle of the carriageway laying the new water main, and so there will be no access available during this time.
When our team leaves the site in the evening, we'll place road plates over our excavations, allowing you to use Perryman’s Lane.