As part of our ongoing programme to improve our water supply network, we're installing 845 metres of new water pipe in Handcross Road and High Beeches Lane, Balcombe.

We've laid a new pipeline in Handcross Road between our water treatment works and the junction with High Beeches Lane.

Work in Handcross Road began on 31 January and as a safety precaution for pedestrians, motorists and our workforce we closed Handcross Road to through traffic only.

Following work in Handcross Road, work was required in High Beeches Lane, under two-way traffic lights.

Access to homes and businesses will be maintained throughout the project.

Project updates

27 January 2023

We’re pleased to say that this scheme is now complete, with the site returned to its original condition.

15 December

Our excavation at the junction in the summer revealed a high number of existing utilities in the area and so we were unable to finish the work as planned. We have reviewed the work required and the options available to us, and will now be installing a new section of pipe. This will take place from Monday 9 December and is expected to take two weeks to complete.

1 June

This scheme has now completed. However, additional work will need to be undertaken at the junction of High Beeches Lane and London Road. This is scheduled for 20th June for two weeks and will take place under temporary traffic lights.

22 April

The team has now laid 746 metres of pipework and the traffic lights have now been set up on High Beeches Lane.

23 March

We have now laid 450 metres of main in Handcross Road and expect to lay another 80-100 metres this week.

3 March

Works are progressing well. We have now laid 165 metres of main in Handcross Road.

11 February

We have now laid 40 metres of main in Handcross Road and undertaken two connections on to the existing pipework.

31 January

Work started on site in Handcross Road.

4 January:

Work has started at the site of our local water treatment works.