Key facts

Location: Glebe Close, Smarden

Work: Replaced 150 metres of water main

Started: Monday 4 August 2025

Completed: Monday 15 September 2025

Investment: £147,000

We replaced an ageing, burst-prone water main in Glebe Close, Smarden.

The water pipes in Glebe Close have burst 17 times in the last five years. This has meant low water pressure and sometimes no water for our customers in the area.

We’re always working to reduce the number of leaks and bursts we have. By replacing around 150 metres of water main, the network in the area will be more reliable.

Project updates



Monday, 15 September 2025
16:32 PM

Project completed

We're pleased to say we've completed our work in Glebe Close, with all new water main laid and now in use.


Thank you to residents for their patience as we carried out this vital project.


Tuesday, 19 August 2025
15:36 PM

Last week, we laid 90 metres of new water main using the directionally drilling method to the left of the cul-de-sac. This section of pipeline is currently being tested and sampled.


This week, once we're happy the testing and sampling has been successful, we'll be connecting customer supply pipes to the new main.


Tuesday, 12 August 2025
08:35 AM

Last week, we set up our working area for the duration of the project and made our first connection to the existing network.


We also prepared the site and excavated the required pits to allow us to install the first section of new water main using the directional drilling method. This will be carried out today. 


This week, we'll be continuing with testing the new mains and preparing the services to transfer from the old pipework to the new main.


Monday, 4 August 2025
14:35 PM

We’re pleased to confirm work has started on our project to replace 150 metres of water main in Glebe Close, Smarden. 

We'll provide further updates as our work progresses and we want to thank local residents for your patience while we carry out this vital work.

Share this Article: