Key Facts
Location: Biddenden Road and Bethersden Road, Smarden
Work: Installing approx. one kilometre of pipeline
Starts: Monday 5 January 2026
Duration: Approx. 14 weeks
Investment: £500,000
Project completed
We’ve laid around one kilometre of new pipeline to replace two existing water mains in Bethersden Road and Biddenden Road, Smarden.
The pipelines were burst-prone, having required 11 repairs in the last five years. By replacing these with a new section of pipework, your water supply will be more reliable, and we can reduce the amount of water lost to leaks and bursts.
Project updates
Tuesday, 5 May 2026
10:30 AM
Project completed
We’ve now completed this project. Thank you to the community for your patience while we improved the water supply network in the area.
Wednesday, 18 March 2026
12:06 PM
Project nearing completion
We’re completing the remaining elements of this project and are aiming to leave the site by the end of this week.
Wednesday, 11 March 2026
11:03 AM
All three connections to the existing network have now been completed and we have seven customer supply pipes left to connect to the new main. We’re aiming to complete these and leave site by the end of this week, around one month ahead of programme.
Thursday, 26 February 2026
09:55 AM
All new pipeline has now been installed and we’ve completed two connections to the existing main, with the third and final connection scheduled for Tuesday 3 March. Next week, once we’ve received successful testing results, we’ll transfer all remaining customer supply pipes to the new main.
Tuesday, 17 February 2026
14:30 PM
Project latest
We’ve now installed more than 1,000 metres of water pipes as part of the project and transferred all customer services on Biddenden Road.
We’ll be carrying out a further connection to our network in Bethersden Road on Thursday (19 February), when there will be a short interruption to supply.
We’ll work as quickly as possible to complete this, to minimise disruption to customers.
Friday, 6 February 2026
08:05 AM
Traffic management change
We’ve reached the completion of work on Biddenden Road, with around 520 metres of new pipeline laid and all customer supply pipes on this section transferred.
We'll be starting to move traffic management into Bethersden Road from today, Friday 6 February. Once we've moved, Biddenden Road will be reopened and Bethersden Road will be closed as we begin to work south from the junction.
Tuesday, 27 January 2026
14:12 PM
We’ve now installed around 500 metres of new pipeline. We’re waiting for testing results on this new main before we connect customer supply pipes and bring it into service. We’re expecting to move into Bethersden Lane in around two weeks and will confirm the exact date shortly.
Monday, 5 January 2026
09:07 AM
Work begins
We've arrived on site to begin this project. We'll work as quickly as we can to complete this scheme as soon as possible.